SCHEDULE

It’s expected that a design development stage will last 15-18 months. Following this stage, SOCAR will round off the negotiations with concerned Chinese companies on engineering, procurement, construction and funding issues based on which it will obtain information sufficient for making of Final Investment Decision (FID). The agreed construction works will take 48 months as of the date of taking a FID decision. The plants are expected to be commissioned in 2022.